Form I-RA/D 140/235 (Version A), Mfg No. 110318 Rev 3, Page 17
Installing
Ducts
Inlet Air Duct
Discharge
Duct
Inlet Air Duct
Canadian installations require field installation of an inlet air duct (re-
turn air system) on a Model RAD heater. The blower-equipped heater has
an inlet air duct flange. Inlet duct dimensions (inside) should be:
RAD140 RAD235
Height 32-1/8” (816mm) 32-1/8” (816mm)
Width 21-3/4” (552mm) 31-1/8” (791mm)
Slip the ductwork over the flange and attach using 1/2” long sheet metal
screws.
Discharge Duct
A discharge duct may be attached to a Model RAD heater. To connect the
duct to the heater,
Remove the louvers from the furnace.
Field fabricate a duct transition as illustrated.
Attach duct transition to the heater using 1/2” long sheet metal
screws
IMPORTANT: Never reduce the furnace opening size
abruptly. Always use a tapered transition like the one
illustrated.
3/4 (19mm)
18
(457mm
minimum)
3/4 (19mm)
3/4 (19mm)
16-1/4 (413mm)
A
B
RAD A Minimum B
140 30” (762mm) 15” (381mm)
235 40” (1016mm) 20” (508mm)
Model RAD 140 235
CFM (free air) 2000 3200
Air throw (9 ft 50 ft 65 ft
suspension) 15M 20M
CFM .25" ESP 1425 2140